Change Orders - What's Fair / What's Not
To add a comment visit the Article Page.
Comments
Mr. B
14 Dec 2007, 10:08
14 Dec 2007, 10:08
I had a garage built by a general contractor. Along the way I had an few
outlets added (by the electrician) and an extra door and hardware ordered
(which I will install myself). The contract to build the garage is very
simple, it only lists the construction and basic payment terms. There was
no mention of "change order" or "upcharge" costs, either verbal or written.
Do I still have to pay the change order fee for any changes made after the
contract was signed?
AsktheBuilder
15 Dec 2007, 13:03
15 Dec 2007, 13:03
Mr. B.,
Let's turn the table 180 degrees. You are a contractor and you agree to do X amount of work for a fixed amount of money. Your customer asks for additional work to be done. Why should you, the contractor, have to pay out of your pocket for this extra work? I am assuming in your situation that the *simple* plans and specifications didn't show these extra items. If this is the case, you made a mistake by not including them. You owe the money if the items were not in the contract.
Let's turn the table 180 degrees. You are a contractor and you agree to do X amount of work for a fixed amount of money. Your customer asks for additional work to be done. Why should you, the contractor, have to pay out of your pocket for this extra work? I am assuming in your situation that the *simple* plans and specifications didn't show these extra items. If this is the case, you made a mistake by not including them. You owe the money if the items were not in the contract.
Mr. B
17 Dec 2007, 18:48
17 Dec 2007, 18:48
Oh my goodness, my apologies for any misunderstanding. I have every
intention of paying for all material and labor costs associated with my
change requests. My question pertains to the additional "upcharges" (25%)
requested by the general contractor. There was no mention of this fee.
AsktheBuilder
17 Dec 2007, 19:29
17 Dec 2007, 19:29
Mr. B,
If that fee was not spelled out, then it is negotiable. But remember the old saying: The mills of the gods grind slowly but thoroughly.
If that fee was not spelled out, then it is negotiable. But remember the old saying: The mills of the gods grind slowly but thoroughly.
To add a comment visit the Article Page.

