Summary: Shower membranes are fairly simple to install. The following is a cross section of a shower floor membrane. By following the instructions and tips found on this chart, your shower will surely be waterproof.

Cross Section of Typical Shower Membrane Installation

If you have ever gone swimming inside an above ground pool, you will easily understand the concept of a membrane shower pan liner. The vinyl swimming pool liner does a great job of keeping water inside the pool. You want your shower pan liner to act in the same manner and keep water within the confines of the liner and subsequently direct it to the shower drain.

The drawing below shows an interesting detail that many plumbers and tile setters fail to do.

Note how the top of the clamping ring drain assembly is flush with the top of the sub-floor plywood. In order to achieve this, the plumber (or jobsite carpenter) needs to rout out a recessed area in the actual sub-floor. Most plumbers don't carry routers in their truck, unfortunately! I used to go to this detail since I had all of the tools. This is an important step. If you don't do this, about 3/16 inch of standing water will always be present in the pan.

Note the top of the adjustable shower drain inlet that rises above the subfloor. This part of the drain assembly screws up and down in order to compensate for the thickness of the cement mud base and the thickness of the finished tile. It is critical to have this drain part in place when you pour the cement mud base. For sake of illustration, I have not shown the cement base or the pea gravel that sits on top of the CPE liner.

Before the mud hardens, you screw it up and down to cut threads into the soft cement mixture. I always make sure that the cement mud mixture is poured below the top of the finished drain an amount equal to the finished thickness of the ceramic tile. You really don't want to crank the drain up and down once the cement mud has dried. Don't forget to install the washed pea gravel above the drain holes in the drain assembly. If you forget this, you may develop a leak.

 





Comments:

mike
19 Dec 2007, 01:52
im putting in a new bath with a precast tub but tiling the walls im concerned about the seams between the backerboard do i need to seal them with something, keep the backerboard half inch off the tub?ive laid tile on floors only,im a rookie on this can you help
AsktheBuilder
19 Dec 2007, 07:36
Mike,
I cover all of these questions and more in ALL of my past columns on ceramic tile backer board. I suggest you take the time to read them.

     View all comments
*Name:
Email:
Notify me about new comments on this page
Hide my email
*Text:
Security Image:

Visual CAPTCHA


 
Contact us to Advertise on this site.
Have a Suggestion?
Do it right, not over!

Ask the Builder Comment Help

Thanks for stopping by! The Comments Section of my AsktheBuilder.com website are a place for you to share stories about how you've solved a similar problem at your home or carry on a conversation with other visitors. I tried, at the beginning, to be part of the conversation, but there were too many questions being asked and it was impossible for me to keep up and get my regular work finished each day.

If you want to ask me a direct question, you should go to the Ask Tim page of this website.

Helpful Comment Tips: If you need help with a problem, please try these things now before you type in a comment. You could discover your answer in just minutes.
Don't show this alert again.