Cost Overruns

By
©1993-2012 Tim Carter

        
Summary: Cost overruns are a nightmare that can be avoided with time invested upfront. Your budget can be maintained by selecting all items and features before you bid out your new home. Bills of the scary kind can be avoided with specific itemization of each feature and elimination of builder allowances.

DEAR TIM: I have had several new homes built for me. I was determined to stay within budget on my most recent project. I had a solid contract, an extensive cost breakdown provided by the builder, a decent set of blueprints and specifications and I still was surprised with a bill for nearly $57,000.00 worth of cost overruns. Please look at my documents and tell me what went wrong. Jim D., Cincinnati, OH

DEAR JIM: The autopsy report is in. There were multiple causes for the cost overruns. The blame can be traced to mistakes on your part and some on the part of the builder. Unfortunately, I have also discovered some evidence that may lead to an indictment on the part of the builder. It appears that there are several items that are being presented to you as overruns that are simply bidding shortfalls made by the builder. These mistakes should be paid for by the builder or deducted from his final payment.

This seemingly innocent pedestal sink faucet could easily create a $900.00 cost-overrun headache.
This seemingly innocent pedestal sink faucet could easily create a $900.00 cost-overrun headache.
Your contract appears to be very good. It is a fixed sum contract that locks in the total cost of the home. The wording of the contract clearly states that the builder will construct the home using the plans and specifications. The contract references the itemized cost breakdown sheet showing each phase of construction. Indeed there is a line item cost for many aspects of the job. The contract further states that the builder will receive a profit and overhead sum of 17 percent in addition to these specific costs. I have no trouble with this method of compensation.

The first problem that I see is that the plans and specifications are missing a considerable amount of detail. For example, I can see exterior trim boards and other woodwork, but the plans do not indicate the type of material nor its size. I see countertops drawn but no material type is mentioned. I see bathrooms but wonder if you are going to get shower doors or curtains, towel bars, toilet paper holders, etc. The plans show that you will have a brick exterior but there is no mention of the level of quality of the actual brick material.


How would you like me to build your new home? It's probably impossible for me to fit your job into my schedule, but I will gladly share hundreds of my tricks and building secrets with you and your builder. Check out my New House Specifications.


I see a line item in the cost breakdown for brick, but it is a big number. There is no separate breakdown for brick labor, sand, mortar, structural steel lintels, flashings, etc. This lack of detail allows a dishonest builder to play the classic shell game. When asked, the builder lowers the actual budgeted cost of an item by artificially puffing the costs of one of the other items within the group.

To avoid this problem area, the cost breakdown for a new home must have a line item for labor and many of the different materials for each phase of the project. This method allows you to see if material costs have been exceeded and if so, whose fault it is. For example, there were several areas where you blew the budget because you selected more expensive fixtures. Your lighting fixtures, plumbing faucets and kitchen cabinets all exceeded the allowance as specified by the builder.

This particular nightmare can be avoided by simply eliminating allowances. Clever builders can insert low allowances to make their overall bid number low. Once you sign the contract and start construction, this flaw becomes painfully apparent. In other words, pre-select ALL fixtures and items and list them in the written specifications before the job is bid by the different contractors. If your bids come in too high, you can lower costs by choosing a less expensive fixture. The builder is trying to take advantage of you in several areas. He is trying to charge you $15,000.00 more for a retaining wall that is clearly shown on the site plan. You have not requested any changes to the wall and it appears to be a straightforward task. Based upon the line item for the wall in the cost breakdown, I feel the builder simply made a mistake and underbid this aspect of the job. He did the same thing with all of the exterior concrete work. I did a quick calculation and determined that you can barely buy all of the concrete for the amount he has provided for in the cost breakdown.

Finally, I see that you requested several changes during construction but that there are no signed change orders. That was a major mistake on your part. Never allow a change to be made unless you are presented with a written change order that both you and the builder sign. The change order should clearly show any additional charge or credit depending upon the nature of the change.



Still Need Help? Type Your Keywords Here:
(examples: drywall repair, pilot light goes out, poor lot drainage, crown molding guide, etc.)

Comment on Facebook

Your Facebook friends would love to know how this column helped you solve your problem. Type a quick comment of what you discovered here at AsktheBuilder.com. Thanks!





Comments:

Welcome! I, Tim Carter, don't answer questions here. If you post a question here in the Comments Area, perhaps another visitor will help you. You need to go to the Ask Tim page if you want a question answered. Once there, look closely at how many weeks behind we are. Please be patient as you use this free service. If you have an emergency and need to talk to me, there is an option there for you.
Brandi
05 Mar 2008, 17:45
We are buliding our home. The contractor has underbid on just about everything, who pays for the difference? He says that we have to, we have a paper that shows how much is allowed for each part of the buliding process. For instance, he did not allow for enough for the foam insulation that we put in and it was in our contract that we would put in foam insulation. He said we had to pay the difference, but isn't it his fault for underbidding it and he have to pay the difference? There have been other issues, such as the deadline for the house that was put in the contract was 7 months ago and counting.
AsktheBuilder
09 Mar 2008, 10:04
Brandi,
You are another victim....... Read the column above again and see how you were duped. The contractor put in unrealistic allowances to get his overall bid lower. It is called Deception. Who is at fault? Unfortunately most of the blame is yours because you should NOT have had ANY allowances in the job. All of this would have been avoided if you would have made exact product selections in the plans and specifications. Go read ALL of the columns in my House Plans and Home Builders categories.
Allowances are Death on a Stick with Bird Flu all over it.....
lisa
21 May 2009, 12:28
Do builders add their mark up to allowance items? I ask because we are building a custom home via a builder. His price listed $9000 allowance for kitchen cabinets. I ened up finding a custom guy to build them, who priced the cabinets at $7000. The builder said he will credit us back the allowance and let us handle it. BUT, did he not have a 10% mark up in his total price, that should be credited back to us as well, if he is not having a part if the cabinet installation? Or does he just give us the credit for the allownace, but still keep the 10% mark up in this overall cost?

     View all comments
*Name:
Email:
Notify me about new comments on this page
Hide my email
*Text:
Security Image:

Visual CAPTCHA


 
Remember, Tim Carter doesn't answer questions here in the comments. You need to go to the Ask Tim page.
 
Have a Suggestion?
Do it right, not over!

Ask the Builder Comment Help

Thanks for stopping by! The Comments Section of my AsktheBuilder.com website is a place for you to share stories about how you've solved a similar problem at your home or carry on a conversation with other visitors. I tried, at the beginning, to be part of the conversation, but there were too many questions being asked and it was impossible for me to keep up and get my regular work finished each day.

If you want to ask me a direct question, you should go to the Ask Tim page of this website.

Helpful Comment Tips: If you need help with a problem, please try these things now before you type in a comment. You could discover your answer in just minutes.
Don't show this alert again.