DEAR TIM: I have had several new homes built for me. I was
determined to stay within budget on my most recent project. I had a solid
contract, an extensive cost breakdown provided by the builder, a decent set of
blueprints and specifications and I still was surprised with a bill for nearly
$57,000.00 worth of cost overruns. Please look at my documents and tell me what
went wrong. Jim D., Cincinnati, OH
DEAR JIM: The autopsy report is in. There were multiple
causes for the cost overruns. The blame can be traced to mistakes on your part
and some on the part of the builder. Unfortunately, I have also discovered some
evidence that may lead to an indictment on the part of the builder. It appears
that there are several items that are being presented to you as overruns that
are simply bidding shortfalls made by the builder. These mistakes should be paid
for by the builder or deducted from his final payment.
 |
| This seemingly innocent pedestal sink faucet could easily create a $900.00 cost-overrun headache. |
Your contract appears to be very good. It is a fixed sum
contract that locks in the total cost of the home. The wording of the contract
clearly states that the builder will construct the home using the plans and
specifications. The contract references the itemized cost breakdown sheet
showing each phase of construction. Indeed there is a line item cost for many
aspects of the job. The contract further states that the builder will receive a
profit and overhead sum of 17 percent in addition to these specific costs. I
have no trouble with this method of compensation.
The first problem that I see is that the plans and specifications are missing
a considerable amount of detail. For example, I can see exterior trim boards and
other woodwork, but the plans do not indicate the type of material nor its size.
I see countertops drawn but no material type is mentioned. I see bathrooms but
wonder if you are going to get shower doors or curtains, towel bars, toilet
paper holders, etc. The plans show that you will have a brick exterior but there
is no mention of the level of quality of the actual brick material.
How would you like me to build your new home? It's probably impossible for me
to fit your job into my schedule, but I will gladly share hundreds of my tricks
and building secrets with you and your builder. Check out my
New House Specifications.
I see a line item in the cost breakdown for brick, but it is a big number.
There is no separate breakdown for brick labor, sand, mortar, structural steel
lintels, flashings, etc. This lack of detail allows a dishonest builder to play
the classic shell game. When asked, the builder lowers the actual budgeted cost
of an item by artificially puffing the costs of one of the other items within
the group.
To avoid this problem area, the cost breakdown for a new home must have a
line item for labor and many of the different materials for each phase of the
project. This method allows you to see if material costs have been exceeded and
if so, whose fault it is. For example, there were several areas where you blew
the budget because you selected more expensive fixtures. Your lighting fixtures,
plumbing faucets and kitchen cabinets all exceeded the allowance as specified by
the builder.
This particular nightmare can be avoided by simply eliminating allowances.
Clever builders can insert low allowances to make their overall bid number low.
Once you sign the contract and start construction, this flaw becomes painfully
apparent. In other words, pre-select ALL fixtures and items and list them in the
written specifications before the job is bid by the different contractors. If
your bids come in too high, you can lower costs by choosing a less expensive
fixture. The builder is trying to take advantage of you in several areas. He is
trying to charge you $15,000.00 more for a retaining wall that is clearly shown
on the site plan. You have not requested any changes to the wall and it appears
to be a straightforward task. Based upon the line item for the wall in the cost
breakdown, I feel the builder simply made a mistake and underbid this aspect of
the job. He did the same thing with all of the exterior concrete work. I did a
quick calculation and determined that you can barely buy all of the concrete for
the amount he has provided for in the cost breakdown.
Finally, I see that you requested several changes during construction but
that there are no signed change orders. That was a major mistake on your part.
Never allow a change to be made unless you are presented with a written
change order that both you and the builder sign. The change order
should clearly show any additional charge or credit depending upon the nature of
the change.